The inability of a munitions plant in Mesquite, Texas, to build a key part set back the U.S. Army’s plans for ramping up production of 155mm shells to 100,000 rounds per month, according to a scathing new report by the War Department’s Office of Inspector General (DOWIG). Despite receiving close to $500 million from the U.S. Army funded through supplemental spending bills from Fiscal Years 2022 and 2023, General Dynamics Ordnance and Tactical Systems (GD-OTS), failed to make a single subcomponent needed to produce the badly needed shells as of last March.
“Without the 30,000 additional projectile metal parts anticipated from the Mesquite facility, the Army will be unable to reach its monthly capability goal of 100,000 155-mm artillery rounds,” the report concluded. “As of March 2026, the CPE A&E [Capability Program Executive Ammunition & Energetics] officials have not developed a plan to produce the additional rounds that are supposed to be produced at the Mesquite facility.”
At present, the Army is only producing 36,000 rounds per month, inspectors revealed.
Through modernization efforts and two new facilities, the Army expects to exceed the 100,000-round-per-month goal significantly by the end of next year. The initial goal was established by Congress in the wake of the U.S. providing millions of rounds to Ukraine.
[...]
The main issue inspectors found was that the plant adapted equipment used to make parts for M107 155mm shells to produce parts for M795 155‑mm shells. The latter is an upgraded version of the munition that is slightly heavier and longer, and has an extended range.
As a result of this adaptation, several factors came into play, according to DOWIG. Army officials knew that the concept of trying to produce the more advanced 155mm shells using equipment not designed for that was risky. However, officials felt that would pay off because that machinery was already available. In addition, the report stated that the existing Scranton plant’s past work with GD-OTS on ammunition production was a factor in deciding to take a chance on what turned out to be a flawed assumption.
[...]
“The contractor has been working since the original contract task order was issued in November 2022 to produce the contracted 155-mm projectile metal parts. However, according to CPE A&E officials, acquiring the equipment and adapting it to produce M795 155-mm projectile metal parts resulted in significant challenges.” The report redacted specific examples.
From the article:
[...]
[...]